Assiut University network is one of the oldest Universities
networks in Egypt as it was established in 1996. It provides
internet service to all the faculties, departments,
laboratories, and Staff of Assiut University.
This project aims at improving the performance, productivity,
security and reliability of the network via upgrading the
network infrastructure, equipment, servers and software. The
project will serve as the main backbone to many major ongoing
projects in the University such as E-learning, digital library,
and University information systems.
The main objectives of the
project can be summarized as follows:
-
Upgrading the network
infrastructure by increasing the main connection rate to the
internet from 2 Mbps to 32Mbps.
-
Improving the network
services via new mail, web, and domain servers in addition
to the required servers for digital library, E-learning and
information system projects.
-
Continuity of network
services by employing uninterruptible power supplies.
-
Improved network
security by providing the network with hardware /software
firewall and anti-virus, anti-spam protection systems.
To fulfill these objectives, the
work plan of the project consists of the following stages.
-
Analysis of the existing
network performance.
-
Proposal of the new network
design, topology and equipment.
-
Purchase of the required
servers, equipment and software.
-
Installation of the
purchased equipment.
-
Operation and testing of the
network.
-
Tuning the network for best
performance.
-
Submission of final report
on the project.
At The end of the project, the
following outcomes will be obtained:
-
Faster connection rate all
over university network.
-
Improved mail and web
service to all the university network users.
-
Continuous operation of the
network services.
-
Enhanced security and
protection against viruses and hackers.
The project goals can be achieved if the required funds have
been allocated to the project according to the project budget
and time plan. Other risks may also face the project progress
such as:
-
The increase in the price of
equipment above that estimated in the project budget.
-
Delays in the delivery of
equipment requested from the contracted companies/vendors
and accordingly, newer updated equipment may emerge.
-
Delay in the installation and operation of the purchased
equipment.